When Kruse Corporation needed to retrofit the basement of the 100-year-old Union Station with a full hydronic piping system, they called on Victaulic for their scan to BIM expertise. The Kansas-based mechanical contractor needed a unique solution for the train station’s tight spatial constraints and a demanding construction schedule, made worse by the Thanksgiving and Christmas holidays. With the help of Victaulic’s Virtual Design and Construction (VDC) team and cutting-edge BIM technology, Kruse saved upwards of 30% on labor costs and cut the build time in half.

 

“… it was a 100-year-old building, and it had a tight window in terms of the schedule,” said Noah Morford of Victaulic. “So it took a lot of thinking outside the box about how this job was going to come to fruition.”

 

Victaulic’s VDC team used a 3D laser scanner to create an exact model of the space, eliminating the risk that comes with measuring the room by hand and detecting potential obstacles before equipment and products even arrive on site. This visualization of the project enabled Kruse to see the bigger picture from the start, catching key errors that would have put them behind schedule.

 

Click here to read the full story, now featured in MCAA’s Smart Solutions Summer 2019 issue. The Mechanical Contractors Association of America (MCAA) features innovative resolutions to construction obstacles in their Smart Solutions seasonal series. Victaulic’s scan to BIM knowledge helped this project overcome its many complications, earning it a spot in the most recent issue.

Victaulic(唯特利)

Victaulic is the leading producer of mechanical pipe joining solutions. Engineered with confidence, our solutions put people to work faster, while increasing safety, ensuring reliability and maximizing efficiency.

Related posts

414 Light Street in Baltimore, Maryland

BIM 软件专业知识帮助 Poole & Kent 项目提前竣工

Find out how Victaulic’s BIM software expertise (Virtual Design and Construction (VDC) team) helped Poole & Kent finish HVAC infrastructure install...

Construction Workers - Shinn Tunnel

Piping Partnership Helps Seattle Contractor Finish Tunnel Project in Ten Weeks

By partnering with Milwaukee and Victaulic, Shinn Mechanical successfully installed, tested and completed a two-mile drain piping system in Seattle...

This HVAC installation at 525 West 52nd Street in New York City was on budget and ahead of schedule

Victaulic VDC Turns In NYC’s Latest Luxury Building On Budget & On Time

With the help of Victaulic's VDC team, Martin Associates successfully installed, tested and completed the HVAC system at 525 West 52nd Street in le...

Recent posts

Victaulic Mechanical Joints Make for Fast & Easy CPVC Pipe Repair

Mechanical Joint Makes for Fast and Easy CPVC Pipe Repair

A mechanical system’s integrity is critical. An innovative joining system helps to ensure fast, reliable CPVC pipe installation and repair.

Nebraska community center chooses Victaulic mechanical couplings as its HDPE joining method for the Geothermal HVAC System project

HDPE Joins Geothermal HVAC System for a Community’s Passion Project

Nebraska community center celebrates timely opening after choosing a mechanical solution as its HDPE joining method on the project.

Raw material sourced to make Victaulic elastomer gaskets and seals

Spotlight on Elastomer Gaskets and Seals

At the heart of each mechanical pipe joint is a strategically designed Victaulic gasket. Learn how the development of our seals adds product assura...