Fabrication Solutions Installed at Permian Basin Production Facility

Permian Basin Production Facility
Wastewater Icon

项目概况

项目类型:
Production Facility
业主:

顾问公司设计院:

承包商:

管道材料:

碳钢

管道尺寸:

2’’ - 8’’

位置:

Permian Basin

解决方案:

  • 制造
  • Project Modeling and Design
  • 压缩项目工期
  • 安装便捷
  • Onsite Training & Support

An owner in the Permian Basin recently completed construction on a new production facility and chose to partner with Victaulic for vertically integrated fabrication solutions. Victaulic’s in-house modeling team worked closely with the owner to design the piping systems within the containment area, on the site separators, and on the oil, water, and vent lines.

The 2’’ – 8’’ system was fabricated at Victaulic’s fabrication shop and delivered in 3 sequential shipments to meet the project’s unique build strategy. Victaulic field engineers were onsite at the time of delivery to provide training and support to the installation contractor and crew. All systems were installed seamlessly, with 95% of the project installed in just over 2 weeks.

Partnering with Victaulic mitigated risk and maximized onsite productivity. The use of Victaulic vertically integrated fabrication solutions enabled the production facility to be brought online on time and on budget.

项目类型:
Production Facility
Wastewater Icon
业主:

顾问公司设计院:

管道材料:

碳钢

位置:

Permian Basin

承包商:

管道尺寸:

2’’ - 8’’

解决方案:

  • 制造
  • Project Modeling and Design
  • 压缩项目工期
  • 安装便捷
  • Onsite Training & Support

An owner in the Permian Basin recently completed construction on a new production facility and chose to partner with Victaulic for vertically integrated fabrication solutions. Victaulic’s in-house modeling team worked closely with the owner to design the piping systems within the containment area, on the site separators, and on the oil, water, and vent lines.

The 2’’ – 8’’ system was fabricated at Victaulic’s fabrication shop and delivered in 3 sequential shipments to meet the project’s unique build strategy. Victaulic field engineers were onsite at the time of delivery to provide training and support to the installation contractor and crew. All systems were installed seamlessly, with 95% of the project installed in just over 2 weeks.

Partnering with Victaulic mitigated risk and maximized onsite productivity. The use of Victaulic vertically integrated fabrication solutions enabled the production facility to be brought online on time and on budget.